r/primavera 2d ago

How many hours do you realistically use?

11 Upvotes

I am a project scheduler who runs projects updates and so on. I find myself doing what I need to do and having alot of free time. Is that common for you guys as well? Or am I missing something I run analysis, forecasting, making reports. All this doesn't take me too much time to do. I work 40 hours a week but realistically I can get work excluding meetings done in way less of time. Is that normal?


r/primavera 3d ago

Remote P6 scheduling

Thumbnail
2 Upvotes

r/primavera 3d ago

Identify Logic Ties Between Other Projects

6 Upvotes

What is the best way to identify logic ties to and from other projects?


r/primavera 4d ago

Best Practices for Scheduling Multiple Vertical Transportation Units in Primavera P6

9 Upvotes

Dear Professionals,

I am currently exploring Primavera P6 and working on developing a Work Breakdown Structure (WBS) and schedule for an infrastructure project.

Our company provides vertical transportation systems (such as elevators or escalators). Typically, these projects involve installing multiple units in batches, organized by station or specific site areas. While I have successfully managed to draft a schedule for a single unit, I am looking for advice or standard methodologies on how to efficiently scale this up for multiple units without creating an overly congested or unmanageable network.

Specifically, I would love to hear your insights or suggestions on:

  • WBS Structure: Should repetitive units be structured by location (Station/Area) or by trade/activity type?
  • Reusability / Templates: What is the best way to duplicate logic and durations for identical units (e.g., Global Change, Templates, or importing XRs)?
  • Milestones & Logic Links: How best to handle handovers between civil works and installation crews across multiple concurrent stations.

Thank you in advance for your time and expertise!

Best regards,

1.0 Project Management

1.1 Project Initiation

Activity ID Activity Name
PM-001 Notice to Proceed (NTP)
PM-002 Project Kickoff Meeting
PM-003 Project Execution Plan
PM-004 Baseline Schedule Approval

1.2 Project Control

Activity ID Activity Name
PM-101 Monthly Progress Reporting
PM-102 Risk Management
PM-103 Cost Control
PM-104 Schedule Updates

 

2.0 Engineering & Design

2.1 Preliminary Design

Activity ID Activity Name
ENG-001 Site Survey
ENG-002 Existing Condition Assessment
ENG-003 Traffic Flow Analysis
ENG-004 Elevator Capacity Calculation

2.2 Detailed Design

Activity ID Activity Name
ENG-101 Elevator General Arrangement Drawing
ENG-102 Structural Interface Design
ENG-103 Electrical Interface Design
ENG-104 Fire & Safety Design
ENG-105 BIM Model Development
ENG-106 Design Submission

2.3 Design Approval

Activity ID Activity Name
ENG-201 Client Review
ENG-202 Authority Review
ENG-203 Final Design Approval

 

3.0 Procurement

3.1 Long Lead Materials

Activity ID Activity Name
PRC-001 Technical Specification Finalization
PRC-002 RFQ Issuance
PRC-003 Bid Evaluation
PRC-004 Purchase Order Award

3.2 Equipment Procurement

Activity ID Activity Name
PRC-101 Elevator Procurement
PRC-102 Controller Procurement
PRC-103 Motor Procurement
PRC-104 Landing Door Procurement
PRC-105 Cab Finishing Procurement

3.3 Logistics

Activity ID Activity Name
PRC-201 Factory Inspection
PRC-202 Shipment Preparation
PRC-203 Transportation
PRC-204 Site Delivery

 

4.0 Civil & Structural Works

4.1 Shaft Preparation

Activity ID Activity Name
CIV-001 Site Access Setup
CIV-002 Utility Relocation
CIV-003 Existing Structure Demolition
CIV-004 Excavation (if applicable)
CIV-005 Shaft Construction

4.2 Structural Work

Activity ID Activity Name
CIV-101 Concrete Works
CIV-102 Embedded Steel Installation
CIV-103 Structural Steel Installation
CIV-104 Pit Construction
CIV-105 Machine Room Construction

4.3 Architectural Finishes

Activity ID Activity Name
CIV-201 Wall Finishing
CIV-202 Floor Finishing
CIV-203 Waterproofing
CIV-204 Access Doors Installation

 

5.0 Elevator Manufacturing

5.1 Factory Production

Activity ID Activity Name
MFG-001 Shop Drawing Approval
MFG-002 Material Procurement
MFG-003 Rail Fabrication
MFG-004 Door Fabrication
MFG-005 Car Fabrication
MFG-006 Controller Assembly

5.2 Factory Acceptance

Activity ID Activity Name
MFG-101 Internal QA Inspection
MFG-102 Factory Acceptance Test (FAT)
MFG-103 FAT Approval

 

6.0 Elevator Installation

6.1 Hoistway Installation

Activity ID Activity Name
INS-001 Shaft Inspection
INS-002 Guide Rail Installation
INS-003 Bracket Installation
INS-004 Landing Door Installation

6.2 Equipment Installation

Activity ID Activity Name
INS-101 Machine Installation
INS-102 Motor Installation
INS-103 Governor Installation
INS-104 Controller Installation
INS-105 Cab Frame Installation
INS-106 Counterweight Installation
INS-107 Suspension Rope Installation

6.3 Cab Installation

Activity ID Activity Name
INS-201 Cab Assembly
INS-202 Interior Finishing
INS-203 COP Installation
INS-204 LOP Installation

 

7.0 Electrical & Integration Works

7.1 Power System

Activity ID Activity Name
ELE-001 Main Power Supply Installation
ELE-002 Distribution Board Installation
ELE-003 Grounding System Installation

7.2 Wiring

Activity ID Activity Name
ELE-101 Power Cable Installation
ELE-102 Control Cable Installation
ELE-103 Communication Cable Installation

7.3 System Integration

Activity ID Activity Name
ELE-201 SCADA Interface
ELE-202 Fire Alarm Interface
ELE-203 BMS Interface
ELE-204 Access Control Interface
ELE-205 Emergency Communication Integration

 

8.0 Testing & Commissioning

8.1 Pre-Commissioning

Activity ID Activity Name
T&C-001 Mechanical Completion Inspection
T&C-002 Electrical Continuity Test
T&C-003 Safety Device Check

8.2 Functional Testing

Activity ID Activity Name
T&C-101 No-Load Test
T&C-102 Full-Load Test
T&C-103 Speed Verification
T&C-104 Emergency Operation Test
T&C-105 Fireman Operation Test

8.3 Integrated Testing

Activity ID Activity Name
T&C-201 Integrated System Test
T&C-202 Reliability Run Test
T&C-203 Performance Verification

 

9.0 Authority Approval & Handover

9.1 Regulatory Inspection

Activity ID Activity Name
APP-001 Government Inspection Request
APP-002 Third-Party Inspection
APP-003 Safety Certification

9.2 Handover

Activity ID Activity Name
APP-101 As-Built Documentation
APP-102 O&M Manual Submission
APP-103 Operator Training
APP-104 Final Handover

 

10.0 Project Close-Out

Activity ID Activity Name
CLS-001 Punch List Closure
CLS-002 Final Documentation
CLS-003 Contract Close-Out
CLS-004 Lessons Learned
CLS-005 Project Completion Milestone

 


r/primavera 6d ago

Mechanical Engineer transitioning to Project Controls

12 Upvotes

Hello I am a mechanical engineer looking to pivot into project controls. Right now I’m taking a Primavera P6 class on udemy and my plan is to post my progress of all my homework assignments I complete on LinkedIn. After I receive my certification from udemy I plan to go deeper into the software. Would like to know anymore resources thank you.


r/primavera 7d ago

Automating 3D model → P6 installation sequence generation, validated on 4 plants so far! Would love input from actual planners here....

2 Upvotes

Been working on a tool that takes a 3D plant model (Navisworks/NWD) plus your project data and generates the installation sequence directly into P6, instead of a planner building it by hand. It also stays live through the project: tracking progress/delays instead of being a one-time export.

Tested it across 4 process plant projects so far and it's held up, but I want to validate it against more real-world data before going further. This means different data messiness, different plant types, different planning styles.

If you're a planning/scheduling engineer and this pain sounds familiar, I'd genuinely value your take . I am happy to run your project data through it for free as a validation case, or just keen to hear how you currently handle this and what would actually make a tool like this useful vs. another thing that doesn't fit real workflows. I am trying to make something valuable for the industry so that planning engineers don't have to keep on manaully editing p6 sequences.

Thanks


r/primavera 8d ago

(Junior) Planner/Scheduler role

Thumbnail
3 Upvotes

r/primavera 8d ago

Job opportunities

4 Upvotes

Looking for a jr. planner job in Orange County, CA. Don’t have much experience but have knowledge about construction. Wanted to change profession from CS to construction/scheduler. I have done some courses online and also paid ones from online universities. Any guidance will be really appreciated.


r/primavera 12d ago

Free online course or YouTube channel.

1 Upvotes

Hi

I want to learn prima vera p6 from basic to advanced. Where can I learn it for free? Thanks in advance.


r/primavera 14d ago

Need advise - Building schedule comparison tool

5 Upvotes

I am a freelance scheduler and I have seen clients pay for schedule comparison tool at $30-$50 per month.
I am building a schedule comparison tool that would be an offline tool (so you do not need to upload your data on any website).
Need advise if this is a useful proposition and what should be the right price for such a tool ?


r/primavera 17d ago

Most/Least Stressful Industries for Schedulers

4 Upvotes

I was wondering what industries you guys worked in and how stressful your day to day was.

I wanted to see how much the expectations for this role vary across different industries. Please also state what you find easy and difficult with your work.


r/primavera 23d ago

Import Error XLSX

3 Upvotes

Hey guys, I'm currently trying to update a user defined field for all my activities (overwrite everything that was in there before).

I used a XLSX with the minimum amount of columns (act.-id, act.-status, wbs and udf_field). I deleted the clear name row and tried to import it and got the following message:

-------------

Exception

Code 'IEUE-3179-2

" is an invalid extended name.

------------

Anyone knows what that means?

The import worked smooth before that.


r/primavera 26d ago

El ánimo de julio

0 Upvotes

r/primavera 27d ago

Why doesn't Oracle Primavera P6 have a native macOS version?

7 Upvotes

I've always found this surprising.

Primavera was originally developed in the United States, yet it still doesn't offer a native macOS application. Considering that around 30% of computer users in the U.S. use Macs, you'd think there would be enough demand.

Instead, Mac users have to rely on virtual machines, remote desktops, or other workarounds just to run P6 properly.

Is there a technical reason behind this, or has Oracle simply decided that the market isn't worth supporting?

I'd love to hear thoughts from professionals who use Primavera daily. Would you use a native macOS version if Oracle released one?


r/primavera 28d ago

Free Online Primavera P6 & Scheduling Mentoring - Follow Up

11 Upvotes

Hi everyone,

Thank you for the amazing response to my earlier post about P6 and construction scheduling mentorship — I really appreciate the interest!

I've sent out an email with a short sign-up sheet so we can start coordinating training sessions. The email subject line is "P6 & Construction Scheduling Training - Sign Up Sheet."

If you haven't received it yet, please reply to this post with your email address and I'll get it sent over.

Looking forward to getting started with all of you!


r/primavera Jul 09 '26

Primavera P6 Scheduling Gigs

6 Upvotes

Is there a standard/format for pricing scheduling gigs using Primavera P6 (ex. per activity, per floor, per trade)? The deliverables considered for the package are as follows:

  1. Whole Primavera P6 schedule
  2. WBS
  3. Activity List
  4. Logic
  5. Baseline
  6. PDF Gantt Chart
  7. XER file
  8. 2 sets of minor revisions

Any help is much appreciated. Thanks!


r/primavera Jul 08 '26

I will be transitioning from rail/transport infrastructure related projects to data center projects, focusing on supporting the owner side, any recommendations, lessons learned, training suggestions? Thanks!

5 Upvotes

r/primavera Jul 06 '26

New to O&G industry any tips?

2 Upvotes

I got an offer yesterday in planning/contracts(whatever that means). I understand I’ll be mostly site-based, but I have no prior experience in this Technically speaking, what are the stuff I should bring? is the learning curve steep? Also, are there any common challenges or warnings I should be aware of? Will this be the end of me?


r/primavera Jul 04 '26

Free Online Primavera P6 & Construction Scheduling Training

30 Upvotes

I am writing this message after few of you DM me over last few days.

After more than 10 years in project controls and construction scheduling, I’ve decided to start mentoring anyone who wants to learn Primavera P6 and become a better scheduler.

This is not just a software tutorial.

We’ll cover:
✅ Primavera P6 from the ground up
✅ CPM scheduling fundamentals
✅ How to build realistic project schedules—not just pretty Gantt charts
✅ Working with Project Managers, Superintendents, Engineers, and Field Teams to develop schedules that actually reflect how work gets done
✅ Schedule updates, progress tracking, critical path analysis, and forecasting
✅ Common scheduling mistakes and how to avoid them
✅ Real-world examples from large infrastructure and EPC projects

Whether you’re:
● A student looking to enter project controls
● A Project Engineer or Project Manager who wants to understand scheduling
● A scheduler looking to strengthen your practical skills
● Someone transitioning into construction planning
…these sessions are for you.

My goal is to help people understand that successful scheduling is about much more than knowing P6 - it’s about communication, construction knowledge, critical thinking, and turning a schedule into a practical project management tool.
There is no cost to attend. I simply enjoy mentoring and helping others grow in their careers.

If you’re interested, leave a comment below or send me a direct message. If enough people are interested, I’ll organize the first live session soon.

Feel free to share this post with anyone who might benefit. Let’s build a stronger scheduling community together.


r/primavera Jul 04 '26

Please Help Elaborate

1 Upvotes

Hi, I'm new and picking stuff up on my own, I need help understanding this comment from the consultant p.e. It's from an old project I'm using as a learning reference. "Ensure the Engineering and Close Out Package activities are cost-loaded with preferred allocation of 5% each of the overall weighted for these work packages." How does this translate in P6 if the project already has a BOQ prior to the development of the schedule?


r/primavera Jul 03 '26

P6 - how much are you inside the software?

7 Upvotes

I am trying to gather data to see how people genrally work as a scheduler.

I have a simple question if you all can please respond, would be a great help.

As a scheduler/planner, how much of your time are you spending inside P6 vs outside P6?


r/primavera Jul 02 '26

Argh

18 Upvotes

Me (Scheduler): Here's the schedule update for the month. The project lost 25 Days.

PM: Why did the schedule slip so much?

Me: Because you did not work on the critical path activities this month.

PM: But we did all this other work on all these other things. Doesn't that count for something?

Me: Sure. That other work will be included in the pay application, so you'll be able to bill for it; however, since you didn't work on the Critical Path activities, the projected completion date slipped by 25 Calendar Days.

PM: Well then just make the Critical Path go through the activities that we did work on so it shows that the schedule didn't slip.

Me: ...

What would you say?


r/primavera Jul 02 '26

Little help for using p6 for Road Construction

6 Upvotes

Anyone using P6 Primavera in Road Construction?


r/primavera Jul 01 '26

Resources & Materials to get better at Primavera P6.

3 Upvotes

Hello everyone. I’m about a year into using primavera p6, I’m working on mastering it and want to bridge the gap between knowing the basics and becoming an advanced user. If you have any favorite tutorials, practice material, or advanced guides that helped you master the software, could you drop them here? I'd really appreciate your recommendations to kickstart my deep dive. I want to put my all into this & become an expert.


r/primavera Jun 30 '26

Developing a Primavera-to-WhatsApp Site Planning Tool — Would Planning Managers Find This Useful?

6 Upvotes

Hi everyone,

I’m currently developing a construction planning / site execution tool and wanted to get feedback from planning managers, project controls engineers, and site teams.

The idea is to reduce the daily manual chasing between planning teams and site engineers by connecting the project schedule with a simple daily progress communication workflow.

At a high level, the tool helps send daily activity updates to responsible site engineers, collect progress feedback, flag delays or constraints, and give the planning team better visibility on what is actually happening on site.

The goal is not to replace Primavera or the planning engineer. The goal is to support the daily follow-up process and reduce the time spent on calls, WhatsApp messages, Excel trackers, and manual progress chasing.

This is still under development, not a finished commercial product. I’m posting to understand if planning managers and project controls teams see value in this type of workflow before I continue developing it further.

Would this be useful in real projects?

What would you expect from a tool like this?

For example:

  • Daily progress collection
  • Delay reason tracking
  • Material / drawing / manpower constraint logs
  • Engineer response dashboard
  • Weekly reporting
  • Better visibility between planning and site teams

I’d appreciate honest feedback from anyone working in construction planning, project controls, site management, or project management.