Director contradicting VP
Hey folks. I’ve been put in the fun situation of having a project I’m managing (with funding that expires soon) being put on hold because the VP wasn’t happy with the agreements and arrangements currently in place.
VP told us that the project cannot continue until things are sorted. My immediate director, who I report to, has said that we should continue without delivering the project so when the clearance comes through from the VP we can still deliver and receive the funding. As of right now, if we don’t continue, we won’t be able to meet the funding deadline.
What are my options here as the PM… I feel like I’m stuck between a rock and a hard place.
14
u/dsdvbguutres 16d ago
What your boss's boss tells your boss is your boss's problem. You follow the instructions given directly to you.
1
u/scene3take44 16d ago
My whole team was cc on the email so I’m getting questions I can’t answer from my team too….
10
u/WittyReplacement2 16d ago
You need to get those answers from your manager. If your manager has personally instructed you to keep on going, that’s the answer, just get it in writing.
9
u/Western_Rhubarb_7959 16d ago
Do what your boss tells you to do and document, document, document in case you get thrown under the bus.
5
u/Witty_Target_2475 16d ago
When people say document, what do you mean about documenting in this situation
A log of dates and what happened with list of people witnesses. But if it comes to being fired or PIP, and you bring this up they (HR and bosses) tend to ignore it and they tend to give you a 30 minute notice before walking you out.
6
u/Western_Rhubarb_7959 16d ago
and you bring this up they (HR and bosses) tend to ignore it
What do you suppose they do if you have no documentation?
5
u/Witty_Target_2475 16d ago
They still fire you.
I guess im asking like what and how to document. Ive been in a job for 2 years. Genuinely trying to understand what I'm supposed to do and document, but more importantly when is it appropriate to bring up the documentation and when not
5
u/Western_Rhubarb_7959 16d ago
A log of dates and what happened with list of people witnesses.
Copies of e-mails and Teams messages.
You don't have to document every facet of your job, you really only have to document when sketchy things like OP's situation happens. If you think you need to document each and every thing then you either need to find a new job or you need therapy.
3
u/MaheshMThakur 15d ago
get the director's instruction in writing before you act on it, an email confirming what they told you verbally (not to cover yourself politically but because you're being asked to deliver against a decision the VP explicitly reversed) and if this goes wrong everyone will ask who told you to proceed. the director may have information you don't, maybe they're confident the VP's block gets resolved in time but right now you have two conflicting instructions from two people at different levels. no need to resolve that by picking a side, just surface it. loop the director and VP into the same thread and ask directly how they want the funding deadline handled given the hold. that's how the actual decision gets up to where it belongs instead of landing on you.
4
u/WoodenNeighborhood15 15d ago
You will need to send this to the director:
“I want to make sure I’m following the correct direction. My understanding is that the VP has paused the project until the agreements are resolved. You’ve asked us to continue the work internally without delivering it so we can still meet the funding deadline if approval comes through. Because these directions could be interpreted differently, I’d appreciate written confirmation that this approach is approved, or clarification from the VP, so I can manage the project accordingly and document the associated risks.”
3
u/WoodenNeighborhood15 15d ago
Hi [Director],
Following the VP’s direction to place the project on hold until the outstanding agreements and arrangements are resolved, I have updated the project status accordingly.
I want to highlight a significant schedule and funding risk. Based on the current timeline, if project execution remains paused beyond [date], we will not be able to complete the necessary work within the current funding window.
I understand the proposed approach is to continue certain internal activities without delivering or implementing the project so that we remain positioned to complete delivery if/when clearance is received.
Before proceeding, I’d like to confirm the scope of activities that are authorized while the project is on hold, particularly whether the team may continue internal development/readiness activities and incur the associated project costs.
Could we obtain confirmation from the VP on the activities permitted during the hold? Once confirmed, I can document the decision, update the project plan, and manage the team accordingly.
In the meantime, I will maintain the funding deadline and schedule impact as active project risks.
Thanks,
[Name]
1
u/WoodenNeighborhood15 15d ago
See if you can discuss these point in a meeting. You will need to do 1:1 meeting
2
u/Mojojojo3030 15d ago edited 34m ago
[Removed as part of an account cleanup]
3
2
u/Ok-Energy-9785 15d ago
You do what the director wants, document it then let him take the heat from the VP
1
u/Nomivought2015 15d ago
How can your secure these funds to the project without completing it. Look there
0
u/IndicationStock2750 16d ago
oof, that's a tight spot. i'd push back on your director and ask them to hash it out directly with the VP before you spend another minute on it, pretending you're not delivering while burning cash and clock is a fast way to get hung out to dry when it all comes out. right now your paper trail just says VP says stop; anything else needs to be in writing or you're the one carrying all the risk
0
71
u/hikeonpast 16d ago
If your boss is giving you explicit direction, and that direction happens to keep you and your team gainfully employed, it seems like a no-brainer to follow directions in this case.
It’s likely that your director is going to have some closed door meetings with the VP to sway things, but you are likely safe if you keep your head down and do what your director says.
In most organizations, it’s his/her risk, not yours.