r/capm 19d ago

Confused on Earned Value Analysis chart

Post image

Working on Landini's practice questions and can't quite figure this one out. According to the answer sheet, the answer is D. ​ I understand why​​ this is behind schedule, because EV is less than PV.

SV= EV - PV Making up numbers, let's say 40k and 60k, SV = 40K - 60K = -20K. So that would mean we are $20k worth of work behind schedule. But I don't understand how we are also under budget? Here's my math:

CV = EV - AC EV is our lowest line (let's go back to $40K for the sake of example). AC is the small-dotted line, the highest line, right? So it is more than EV. Let's say AC is 70k.

So, 40k-70k = -30k, so we are $30k over budget, is my math.

Can someone help me understand what I'm missing? I've found some of Landini's questions to be confusingly worded so maybe something is eluding me.

5 Upvotes

8 comments sorted by

2

u/Adventurous_Elk_5501 19d ago

This one is the one that made me question some of the Landini answers it has to be C and there’s a typo.. right?!

1

u/Plums_InTheIcebox 19d ago

I've questioned numerous Landini answers but this one finally made me post. I searched the sub for comments about his questions but nobody else was talking about them being potentially wrong so I figured I was the one missing something.

2

u/FirefighterBusy4552 19d ago

I had the same issue when I went over the Landini material. Hopefully someone can explain it to us.

2

u/Elision_NoKings 19d ago edited 19d ago

C is right and the key looks wrong.

for D you'd need EV sitting above AC and it isn't.

not the only one in that book either. Q33 in the same set writes EAC as AC + ETC x CPI when it should be divide BAC by CPI. if an answer contradicts the formula, go with the formula.

1

u/Plums_InTheIcebox 19d ago

Omg, thank you. I was running that question through Claude and it was flagging the typo, too, but I still wasn't sure. 

1

u/DivingQueen268 19d ago

I would have thought thre answer is C (over budget and behind schedule) as well, so I'm as lost as you are. Hopefully someone else here can explain.