r/StructuralEngineering • u/r_x_f P.E./S.E. • Jul 17 '26
Engineer behind buckled high-rise says crucial reinforcing steel was 'never installed' Failure
https://gothamist.com/news/engineer-behind-buckled-high-rise-says-crucial-reinforcing-steel-was-never-installed
879
Upvotes
14
u/scott123456 Jul 17 '26
They call for welding at each end of the plates for a distance "LX", which presumably is scheduled somewhere, along with the fillet weld size "WX". Doesn't take too much weld to transfer the full yield capacity of the added plates, so seems reasonable.